PROCEDURES FOR SUBMITTING APPLICATIONS TO GCUA

FOR ENDORSEMENT FOR NJDEP PERMITS (TREATMENT WORKS APPROVALS)


Pursuant to N.J.A. C. 7:14A-23.3, et seq. certain activities require a Treatment Works Approval from the N.J. Department of Environmental Protection (NJDEP). When such an approval is required, the applicant must adhere to the following procedures in order to obtain the necessary GCUA endorsements:

Step 1: GCUA Endorsement for Construction of Project

Each application must be reviewed by the GCUA Staff and be presented to the GCUA Board of Commissioners for formal endorsement (by Resolution) at a Public Meeting.

(NOTE: GCUA Board Meetings are held on the 2nd and 4th Wednesday of each month.)

Every effort is made by GCUA to process applications as quickly as possible. In order to ensure the timely review and endorsement of an application, the Applicant must adhere to the following procedures:

Requirements for a Completed Application

1) Project Checklist

2) GCUA's Application Form #CON-94 (original), signed by the local Municipality/MUA

3) Two (2) original signed and sealed (embossed) copies of NJDEP Treatment Works Approval Permit Application Form TWA-1

4) Two (2) copies of Notifications to Local Agencies by certified mail (return receipt requested)

5) Two (2) original signed and sealed (embossed) copies of NJDEP Form WQM-006, with
cost estimate attached. NOTE: Four (4) copies must be submitted when the project includes a metering station

6) Two (2) sets of construction specifications, each with original signatures and embossed seal. NOTE: Four (4) sets must be submitted when the project includes a metering station

7) Two (2) sets of final plans and profiles, originally signed and sealed (embossed) on each
sheet. NOTE: Four (4) sets must be submitted when the project includes a metering station

8) Two (2) original signed copies of NJDEP Statements of Consent Form, WQM-003.
A certified copy of the Resolution from the Municipality/MUA approving the project
must be attached

9) Two (2) copies of GCUA Dry Sewer Affidavit with original signatures and Notary Public
on each copy

10) Two (2) Copies of U.S.G.S. Map with the project site appropriately outlined.
If applicable, attach certification from local engineer that project is located within the
delineated GCUA Service Area

Following endorsement by the GCUA, the project package will be returned to the Applicant for submission to the NJDEP. Upon receipt of the Treatment Works Approval (Permit) from the NDJEP, the application can proceed to Step 2.

STEP 2

GCUA Allocation of Capacity

ALL projects having NJDEP Treatment Works Approvals issued after July 20, 1977 MUST

receive an Allocation of Capacity from the GCUA prior to the introduction of wastewater flow into the sanitary sewers.
 

An applicant may request an Allocation of Capacity for his project provided that the NJDEP Permit is valid (not expired) at the time of the request. (It is the Permittee's responsibility to ensure that the NJDEP Permit has not expired and that all Special Provisos of the Permit, if any, have been complied with at the time of his request to the GCUA).
 

The GCUA will grant Allocation(s) of Capacity in accordance with its Policy and Procedures in effect at the time the application is received. A copy of the Authority's prevailing Policy and Procedures may be obtained upon request.
 

Each application for Allocation of Capacity must be presented to the GCUA Board of Commissioners for approval at a scheduled Public Meeting. The following procedure will bestrictly adhered to:
 

Requirements for a Completed Application
 

1) GCUA's application form #ALL-94 (original), signed and sealed by the local Municipality/MUA

2) Address List (use GCUA form #AL-1)

3) Proof of ability to begin construction of the project within 120 days of the date on which

the GCUA approves the applicant's request for an Allocation of Capacity. GCUA will

accept as adequate "proof of construction" a copy of any one (1) of the following:

a) an executed contract for construction of the sanitary sewer

b) a bond relative to the construction of the sanitary sewer

c) a sworn affidavit (notarized) that construction has been initiated

4) GCUA Construction Expansion Fees (In accordance with Schedule I)
 

Following approval of the application, the GCUA will issue a Construction Expansion Fund Permit (s) to the project owner. The necessary forms (for approval to operate the sewer system) will be forwarded by GCUA to the Municipality/MUA for endorsement of either a partial or final "operating permit".
 
 

STEP 3

Approval To Operate



Upon Completion of the project, application must be made to the local Municipality/MUA, GCUA and the NJDEP (when required by the NJDEP) for operation of the sanitary sewer system. In the case of partially completed projects, partial operation approval is required.

Requirements for a Completed Application

Approval to Operate (Partial)

Approval to Operate (Final) Operation (including partial operation) of the sanitary sewer system CANNOT proceed until all approvals to operate have been granted.



******************************************************************************

If you have any questions on any of the procedures outlined in these instructions please contact:
Eileen Grundlock, GCUA's Developing Projects Coordinator, at (609) 423-3500.