Reading or Exam Tentative Date
Introduction (Ch 1) & Water Treatment Processes (Ch 3) No Quiz, complete reading before Jan 28
Water Quality (Ch 2) Quiz 1 on Feb 1
Basic Design Considerations (Ch 4) Quiz 2 on Feb 8 (Only 4.6)
Predesign Report & Problem Definition (5.1 - 5.3) No Quiz, complete reading before Feb 13
Raw Water Intake, Screening, & Aeration (6.1 - 6.5) Quiz 3 on Feb 13
Flow Measurement (7.3 - 7.5) No Quiz, complete reading before Feb 20
Coagulation, Flocculation, & Precipitation (8.1 - 8.5) Quiz 4 on Feb 22
Sedimentation (9.1 - 9.3) Quiz 5 on March 25
Exam 1 March 15 - Up to and including Mixing and HW 4
Filtration (10.1 - 10.8) Quiz 6 on April 9
Color, Taste, & Odor Control (11.1 - 11.3) No Quiz, complete reading before April 15
Disinfection & Fluoridation (12.1 - 12.2) Quiz 7 on April 22
Exam 2 April 26 - Coagulation, Flocculation, & Precipitation to Adsorption (8, 9, 10, 11), HW 5 - 7
Water Stability & Clearwell (13.1 - 13.3) No Quiz, complete reading before April 29
Residuals Processing & Disposal (14.1 - 14.3) No Quiz, complete reading before May 13
Plant Siting, Layout, Yard Piping, & Hydraulic Profile (15.1 - 15.4) No Quiz, complete reading before May 3
Design Summary (17) No Quiz, complete reading before May 6
Final May 13 - 10:15-12:15